Project Summary
Paul Hemmer Company served as the general contractor on the 165,407 square-foot distribution facility in Hebron, KY. The building measures 640 feet by 260 feet and features a 32-foot clear height, insulated structural precast concrete wall panels, and a mechanically attached 45-mil white TPO roofing system. The building shell includes 13 fully equipped dock positions, 2 grade-level drive-in doors, and an ESFR fire suppression system, with mechanical, plumbing, electrical, and fire protection systems delivered as an integrated design-build package. The specification also carried a comprehensive suite of alternate pricing for a future speculative office fit-out, reflecting the building's readiness for multi-use tenant configurations.
Key Features
- Construction Type: Precast
- Clear Height: 32′
- Dock Doors: 13 plus 2 drive-ins
- Column Spacing: 50′ x 53’4″