Project Summary
Paul Hemmer Company completed a 30,850 SF building modification and expansion at Mazak’s South facility in Florence, Kentucky to support new production operations. The project included demolition of portions of the existing building and slab, construction of a new 67-foot-wide industrial addition, and integration with the existing manufacturing facility. The expansion added new production floor space, support offices, and mechanical infrastructure designed to accommodate future overhead crane systems and advanced manufacturing equipment.
Additionally, Hemmer completed an expansion of Mazak’s National Parts Center shipping and receiving bay totaling 7,000 sq ft.
Key Features
- Approximately 1,700 SF of new office space integrated into the plant
- Structural steel framing designed to support future 5-ton and two 3-ton bridge cranes
- 7" industrial concrete floor slab over engineered base
- 45-mil TPO roof system with R-20.5 insulation
- Metal wall panel exterior system with fiberglass insulation
- High-capacity mechanical systems including multiple packaged rooftop units and HVAC equipment